CLIENT EXPERIENCE

PROJECT: Los Angeles World Airports – LAX Terminal Core Interface

COVA’s CLIENT: Elevators Etc., Inc.

Prime: Austin Commercial, L.P. | Tier 1 Subcontractor: Elevators Etc., Inc. |Tier 2 -Subcontractor: Cova Partners, LLC

Duration: June 2019 to June 2021

Description of Services: COVA will support Elevators Etc. with critical back-office support services.

  • BIM specialist utilizing crossover model software
  • Project Coordination
  • Scheduling
  • Safety Coordination

PROJECT: Los Angeles Stadium & Entertainment District (LASED)

COVA’s CLIENT: Martin-Nevell, joint venture (MNJV)

Prime: Turner-AECOM-Hunt | Tier 1 Subcontractor: Martin-Nevell, JV |Tier 2 Subcontractor: Cova Partners, LLC

Duration: June 2018 to August 2019

Description of Services: BIM Coordination – Modeling for the delivery of wall systems composed of 50,555 sf of plaster for 8 levels, build out framing and drywall for 2 levels as well as 75,000 sf of scaffold at a value of $62 million.

  • BIM specialist utilizing crossover model software
  • Production of large volumes of detailed shop drawings for the field
  • Delivery of drawing for wall systems

COVA’s CLIENT: Mori Consulting, LLC

Prime: Turner-AECOM-Hunt | Tier 1 Subcontractor: Southwest Steel |Tier 2 Subcontractor: Mori Consulting, LLC | Tier 3 Subcontractor: Cova Parnters, LLC

Duration: February 2018 to March 2019

Description of Services: Staff Augmentation – On-Site Project Coordinator

  • Supported Project Manager overseeing fabrication and installation of miscellaneous steel.
  • Document Control – Management and Delivery of Shop Drawings
  • Request for Information (RFI) Coordination

COVA’s CLIENT: Mori Consulting, LLC

Duration: June 2017 to March 2019

Prime: Turner-AECOM-Hunt | Tier 1 Subcontractor: SME Steel |Tier 2 Subcontractor: Mori Consulting, LLC | Tier 3 Subcontractor: Cova Parnters, LLC

Description of Services: Staff Augmentation – On-Site Project Coordinators

  • Vendor Management and Cost Control Tracking & Invoicing
  • Document Control of Thousands of Plans for the Steel Subcontractor
  • Administrative Support for the Coordination of 250 Steelworkers

PROJECT: Community College Opportunities – San Bernardino Community College District & Chaffey Community College District

COVA’s CLIENT: Kitchell (Inland Empire Construction Management Team)

Prime: Kitchell | Subcontractor: Cova Partners, LLC

Duration: April 2019 to Present

Description of Services: Community Outreach – Kitchell selected Cova as their “community outreach” partner for the San Bernardino Community College District and Chaffey Community College District pursuits. Joined the Kitchell team on these particular pursuits to provide future community outreach support in the Inland Empire areas.

PROJECT: Residential Development in the City of Los Angeles

COVA’s CLIENT: Pueblo Properties, LLC

Development Support: Cova Partners, LLC

Duration: September 2019 to End of Project, projected 2022

Description of Services: COVA will provide multiple services for the overall project scope which includes pre-development services ranging from project coordination of the highest and best use of the 1 acre property by identifying architects, soils testing professionals, and other related vendors for the Owner. COVA will ultimately coordinate all project coordination for the future development.